Constructed: 2007

Main Contractor: Savory Construction

Post Tension: BBR Contech

Concrete: Allied Concrete

With a 9000m2 freezer operating at -18 degrees this was constructed as a 180mm thick Post Tensioned slab in three pours but tensioned together to form a jointless slab.

The ELA was constructed as a seperate post tensioned slab.

Aquron 1000 was used for anti-dusting and to provide gloss to the slab.